NEW QUESTION 36
You uploaded suppliers using the mass registration invitation through the Supplier Management Administration and it states there are errors. What action do you perform?

  • A. Change the suppliers information through the SM Administration UI.
  • B. Correct the whole file and re-upload.
  • C. Select Send Invitations and correct the supplier information within the supplier record.
  • D. Correct the suppliers that hat errors and upload the subset of suppliers.

Answer: B

 

NEW QUESTION 37
Where should you create a new KPI according to SAP Ariba's best practice?

  • A. In a project-level master scorecard
  • B. In your personal workspace
  • C. In the sourcing library
  • D. In an SAP Ariba Supplier Information and Performance Management template

Answer: C

 

NEW QUESTION 38
Your customer successfully performed the disqualification process on a supplier. What happens next to the supplier with regards to their commodity and region status?

  • A. Any preferred supplier status for the disqualified commodity categories and regions is automatically removed.
  • B. Their bids are removed from in progress sourcing events using this commodity and region combination in which they have participated.
  • C. The supplier CANNOT be qualified for that specific commodity and region category again.
  • D. Their preferred status is removed and the qualification process starts automatically to requalify them

Answer: A

 

NEW QUESTION 39
When does the Registration tile initially appear in the supplier 360° profile?

  • A. When the supplier registration is pending approval.
  • B. When the supplier request is submitted.
  • C. When the supplier request is approved.
  • D. When the supplier registration is approved.

Answer: C

 

NEW QUESTION 40
Which of the following activates can you perform within the Qualification tile?
Note: There are 3 correct answers to this question.

  • A. View supplier's answers to qualification questionnaires.
  • B. View internal user's answers to disqualification questionnaires.
  • C. Approve or deny the qualification or disqualification if you are in the approval flow.
  • D. Track the progress of the registration process on the status graph.
  • E. View current preferred category status information.

Answer: A,B,C

 

NEW QUESTION 41
Which of the following supplier registration methods are available in SAP Ariba Supplier Lifecycle and Performance?
Note: There are 3 correct answers to this question.

  • A. The system automatically invites the supplier to register after the supplier request is approved.
  • B. An internal user imports the supplier registration questionnaire directly to the supplier's profile.
  • C. The supplier submits a registration request to the customer on SAP Ariba Discovery.
  • D. An internal user performs a mass registration after importing the supplier records.
  • E. An internal user invites the supplier to register after the supplier request is approved.

Answer: A,D,E

 

NEW QUESTION 42
You need to prepare three future iterations of a scorecard and survey. Which action do you perform?

  • A. Copy a previous occurrence as many times as needed.
  • B. Create a new task to trigger each new iteration.
  • C. Manually trigger future recurrences from the master occurrence.
  • D. Create a new folder on the documents tab which contains the master scorecard and survey for each new recurrence.

Answer: C

 

NEW QUESTION 43
Which activities occur as part of the pre-grading process?
Note: There are 2 correct answers to this question.

  • A. The pre-graded value must be approved before the survey can take place
  • B. The system automatically assigns the pre-determined grade for each participant response.
  • C. The grade is pushed to the scorecard.
  • D. The default answer needs to calibrate the scoring.

Answer: B,D

 

NEW QUESTION 44
The SAP Ariba Supplier Management portfolio consists of which solutions?
Note: There are 3 correct answers to this question.

  • A. SAP Ariba Supplier Risk
  • B. SAP Ariba Network Supplier Services
  • C. SAP Ariba Supplier Information and Performance Management
  • D. SAP Ariba Supplier Lifecycle and Performance
  • E. SAP Ariba Supply Chain Collaboration

Answer: A,C,D

 

NEW QUESTION 45
You applied an update to the Team Member Rules file in a template and published the template for SAP Ariba Supplier Performance Management projects. However, the projects you created two weeks ago does NOT reflect this updated file. Why is this the case?

  • A. A deactivated template was used for the project.
  • B. A user must edit the project and accept the changes.
  • C. The template upgrade option was disabled.
  • D. The field labels in the file are incorrect.

Answer: C

 

NEW QUESTION 46
A user is NOT the event or project owner.
Which of the following system groups grant the ability to create and mange surveys?
Note: There are 2 correct answers to this question.

  • A. SPM Agent
  • B. Supplier/Customer Manager
  • C. Supplier/Customer Agent
  • D. Sourcing Agent

Answer: B,C

 

NEW QUESTION 47
Which integration methods can you use when you integrate SAP Ariba Supplier Lifecycle Management with an ERP system?
Note: There are 2 correct answers to this question.

  • A. RESTful web service
  • B. IDoc
  • C. MuleSoft
  • D. SAP Master Data Governance foundation

Answer: A,D

 

NEW QUESTION 48
For SAP Ariba Supplier Information and Performance Management (classic architecture), which SAP Ariba modules can provide data for the supplier 360° report?
Note: There are 3 correct answers to this question.

  • A. SAP Ariba Sourcing
  • B. SAP Ariba Spend Analysis
  • C. SAP Ariba Contracts
  • D. SAP Ariba Supply Chain
  • E. SAP Ariba Discovery

Answer: A,B,C

 

NEW QUESTION 49
Which of the following templates will NOT be activated during the initial deployment of SAP Ariba Supplier Lifecycle and Performance?

  • A. Supplier qualification template
  • B. Default supplier workspace template
  • C. Supplier request template
  • D. Supplier registration template

Answer: B

 

NEW QUESTION 50
Which of the following is a benefit of using SAP Ariba Supplier Performance Management?

  • A. Identify issues with a supplier and create corrective action plans.
  • B. Manage supplier qualifications and preferred supplier designations.
  • C. Collect supplier registration, certification, and banking details
  • D. Track immediate and pipeline savings attributed to a supplier.

Answer: A

 

NEW QUESTION 51
Your customer is working with a supplier who was created from an approved supplier request. The supplier's registration status is Invited.
Which of the following attributes are available in the supplier's 360° profile?
Note: There are 3 correct answers to this question.

  • A. Category status area
  • B. Contacts tab
  • C. Supplier request information
  • D. Approval task for supplier registration
  • E. Qualification tile

Answer: B,C,E

 

NEW QUESTION 52
Your customer wants a question to be answered by an enterprise user and appear in the supplier's 360° profile.
Which option do you recommend?

  • A. Internal survey
  • B. Custom fact table
  • C. Custom header field
  • D. Supplier registration questionnaire

Answer: A

 

NEW QUESTION 53
After a supplier is registered, which of the following activities can be performed within the Registration tile?

  • A. View the registration approval flow.
  • B. Update the primary supplier contact.
  • C. Access the supplier request form.
  • D. Request preferred status.

Answer: A

 

NEW QUESTION 54
You are creating a new SAP Ariba Supplier Performance Management template from scratch. What does SAP Ariba recommend to include?
Note: There are 3 correct answers to this question.

  • A. Recurrence phase
  • B. Scorecard document
  • C. SPM analysis report
  • D. Survey document
  • E. Folder

Answer: B,D,E

 

NEW QUESTION 55
When you create an SAP Ariba Supplier Performance Management template, what are conditions used for?
Note: There are 2 correct answers to this question.

  • A. To control the visibility of project groups on the team tab
  • B. To automatically publish scorecards in the project
  • C. To restrict which supplier can be added to the project
  • D. To control the visibility of documents, folders and tasks

Answer: A,D

 

NEW QUESTION 56
Your customer recently qualified a supplier for IT services in Europe. Which of the following actions can take place now?
Note: There are 2 correct answers to this question.

  • A. The supplier can be disqualified for all commodities in Europe.
  • B. The supplier can be disqualified for IT services in Germany.
  • C. The supplier can be designated as preferred for IT services in the United Kingdom.
  • D. The supplier can be designated as preferred for all commodities in the United Kingdom.

Answer: B,C

 

NEW QUESTION 57
Why would you export a project template?

  • A. To deactivate the project template
  • B. To use it for another customer site
  • C. To use the data outside of SAP Ariba
  • D. To deploy a new template from test to production

Answer: D

 

NEW QUESTION 58
Your customer needs to adjust the scoring weight for a KPI based on contractual standards with a particular supplier.
Where should you edit the scoring based on SAP Ariba 's best practice?

  • A. In the template-level master scorecard
  • B. In the sourcing library
  • C. In the project-level master scorecard
  • D. In the project-level period scorecard

Answer: C

 

NEW QUESTION 59
......