NEW QUESTION 25
Which 'Member Preference' automatically finds the most available resource(s) from the group and allocates to a plan using the allocation action?
- A. Any member and specific member.
- B. All members.
- C. Any member.
- D. Specific member.
Answer: C
NEW QUESTION 26
An it_project_manager can request resources by which of the following: (Choose two.)
- A. Person Days.
- B. Month.
- C. Hours.
- D. Day.
Answer: A,C
NEW QUESTION 27
What system role is needed to manage programs?
- A. it_program_manager_admin
- B. it_program_manager
- C. it_portfolio_manager_admin
- D. it_project_manager
Answer: B
NEW QUESTION 28
Which plugin provides a layer of artificial intelligence that empowers features and capabilities across applications to provide better work experiences?
- A. Predictive Intelligence for PPM [com.snc.ppm_ml]
- B. Strategic Spend Tracking for PPM [sn_ppm_sst]
- C. Scenario Planning for PPM [sn_pw_scenario]
- D. PPM Standard [com.snc.financial_planning_pmo]
Answer: A
NEW QUESTION 29
Who can submit Ideas?
- A. Any IT user.
- B. Any ITIL user.
- C. Any user.
- D. Any demand user.
Answer: C
NEW QUESTION 30
This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.
- A. Stakeholder registry.
- B. Application registry.
- C. Demand form.
- D. Project form.
Answer: A
NEW QUESTION 31
How does a project manager request a change to a resource plan in the requested state?
- A. Use notes on resource plan.
- B. Email resource user.
- C. Request change on resource plan
- D. Email resource manager
Answer: C
NEW QUESTION 32
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)
- A. If the project state is Pending or Open, planned start date and planned end date are displayed.
- B. If the project state is On Hold, actual start date and actual end date are displayed.
- C. If the project state is Draft, actual start date and actual end date are displayed.
- D. If the project state is Work in Progress, actual start date and planned end date are displayed.
Answer: A,D
NEW QUESTION 33
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)
- A. Demand.
- B. Project.
- C. Fixed Asset.
- D. Configuration Item (CI).
- E. User.
Answer: C,D,E
NEW QUESTION 34
When setting-up a program, planned ROI% is calculated based on: (Choose two.)
- A. Values in the NPV field.
- B. Values in the Planned return field.
- C. Values in the Planned cost field.
- D. Values in the Budgeted cost field.
Answer: B,C
NEW QUESTION 35
Which capability allows users to view variances in a project's schedule?
- A. Machine-learning algorithms
- B. Move project
- C. Compare scheduled baselines
- D. Project Status Report
Answer: C
NEW QUESTION 36
In which table can you find cost information for a specific fiscal period?
- A. cost_plan_breakdown
- B. cost_plan
- C. expense_line
- D. pm_project
Answer: A
NEW QUESTION 37
The hourly rate is derived from the resource rate on the resource plan, if this option is selected.
- A. Labor rate card
- B. Rate override
- C. Planned cost
- D. Rate model
Answer: D
NEW QUESTION 38
Which of the following states appear in the process flow indicator at the top of the Demand form by default?
(Choose three.)
- A. Updated
- B. Draft
- C. Screening
- D. Approved
- E. Deferred
Answer: B,C,D
NEW QUESTION 39
Demand managers can enhance a demand request by adding the following: (Choose three.)
- A. Problems
- B. Decisions
- C. Requirements
- D. Stakeholders
- E. Change Requests
Answer: B,C,D
NEW QUESTION 40
What creates calendar entries on a users individual calendar? (Choose two.)
- A. Allocated resource plan.
- B. Confirmed resource plan.
- C. Planned resource plan.
- D. Approved resource plan.
Answer: B,C
NEW QUESTION 41
In what way would you restrict the assigned to field on a project task to only allow users with resource allocations to be assigned?
- A. On the project record under the preferences tab select the "Derive assignee list from resource plan" preference.
- B. The system automatically does this and can only be disabled by an admin.
- C. Create an Access Control List (ACL) rule.
- D. Create a reference qualifier on the 'assigned to' field.
Answer: A
NEW QUESTION 42
In the base system, what is the default number of cards that can be displayed in the project workspace?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
NEW QUESTION 43
Projects and which other artifact can be linked to either a program, a portfolio, both, or neither.
- A. Resources
- B. Test Cases
- C. Demands
- D. Stories
Answer: C
NEW QUESTION 44
......
Certification Training for CIS-PPM Exam Dumps Test Engine: https://www.prep4sureexam.com/CIS-PPM-dumps-torrent.html